71、

New information technology includes( ).

A、Data Engineering

B、Information Security

C、Metaverse

D、Artificial Intelligence

72、

( )are the major issue that Mobile Internet needs to face and deal with.

A、Storage and computing

B、Communications and transmission

C、Data security and privacy protection

D、Intelligent application and interface interaction

73、

( )is the input of project quality management.

A、Project management plan 

B、Data Analysis

C、Risk register

D、Test report

74、

The project manager can arrange the project schedule management activities in the following order:( ).

① Plan Schedule Management ② Define Activities 

③ Estimate Activity Durations ④ Sequence Activities

⑤ Control Schedule ⑥ Develop Schedule

A、 ①②③④⑤⑥

B、 ②④③⑥⑤①

C、 ①③④②⑥⑤

D、 ①②④③⑥⑤

75、

The information security attribute and objectives are( ).

A、Confidentiality, Integrity and Availability

B、Confidentiality, Non-repudiation and shareability

C、Confidentiality, Stability and Availability

D、Confidentiality, Non-repudiation and Availability