摘要:2018上半年信息系統(tǒng)監(jiān)理師考試已經(jīng)結(jié)束,以下為大家整理了2018上半年信息系統(tǒng)監(jiān)理師上午真題第八部分,供考生們參考。
●The information is circulated through communication processes._(71)is not included in Work Performance Information.
(71) A. The status of deliverables
B. Implementation status for change requests
C. Forecasted estimates to complete
D. Work performance report
●(72) is not included in Information Security Risk Assessment Process.
(72) A. Establishing information security risk criteria
B. Identifying the information security risks
C. Formulating an information security risk treatment plan
D. Analysing the information security risk
(73) is not included in Perform Integrated Change Control Process.
(73) A. Defining subsidiary plans
B. Approving changes
C. Managing changes to deliverables
D. Reviewing all change requests
●Every documented change request needs to be ei ther approved or rejected by a responsible individual sually(74).
(74) A. the project sponsor
B. an individual
c. any stakeholeder
D. quality controller
●_(75)in not inc1uded in Control Quality input documents.
(75) A. Project management plan
B. Project documents
C. Quality problems report
D. Work performance data